Wednesday, March 7, 2012

Log Wed 7 March 2012

Accomplished:
-finished S&D E report

Goals:
-begin poster for Design Presentation

Monday, March 5, 2012

Log Mon 5 March 2012

Accomplished:
-wrote most of SE report

Goals:
-finishe SE report
-add pictures to self evaluation report

Friday, March 2, 2012

Log Fri 2 March 2012

Accomplished:
-turned in testing report
-ran chemical analyses on water samples, water fulfills all chemical parameters
-began typing up outline for self & design evaluation

Goals:
-complete at least 3 parts of S&DE
-write up mentor contacts

Tuesday, February 28, 2012

Log Tue 28 February 2012

Accomplished:
-finished 96-hour testing period, collected device from testing site
-collected several water samples

Goals:
-run chemical analyses on water samples
-add results to testing report and finish conclusion

Friday, February 24, 2012

Log Fri 24 February 2012

Accomplished:
-completed 24-hour testing period
-recorded results

Goals:
-complete 96-hour testing period
-record results

Wednesday, February 22, 2012

Log Wed 22 February 2012

Accomplished:
-finalized permissions to test at MCVSD Career Center Greenhouses
-began assembling testing materials (pH strips, refractometer, coliform indicator etc)
-measured transport vehicle area to optimize positioning of device

Goals:
-complete testing 23-24 February
-complete Testing Report

Saturday, February 18, 2012

Log Fri 17 February 2012

Accomplished:
-added more pictures for testing report
-formulated agenda for testing days 23-24 February


Goals:
-find directions to testing site
-gain formal permissions to test
-begin gathering testing materials

Wednesday, February 15, 2012

Log Wed 15 February 2012

Accomplished:
-Final Product awaiting grading
-Testing Stages Explanation Complete
-added some pictures to Testing Report

Goals:
-add more pictures to Testing Report
-Start Self Assessment Report

Monday, February 13, 2012

Log Mon 13 Febuary 2012

Accomplished:
-contacted MCVSD Career Center re: scheduling of testing
-Finished Testing Report Intro and Procedure List
-started Testing Report Stages Explanation

Goals:
-Testing Report Stages Explanation
-Final edits on final product

Wednesday, February 8, 2012

Log Thursday 9 February 2012

Accomplished:
-contacted mentor
-set date for MCVSD Testing on 22 February 2012

Goals:
-contact MCVSD Career Center to finalize testing time/schedule/etc
-make final edits to final product in preparation for assessment
-continue writeup of Testing Report

Monday, February 6, 2012

Log Mon 6 February 2012

Accomplished
-contacted mentor re: EcoComplex testing site
-recieved rubric and due dates and filled calendar schedule
-gained testing site permission from MCVSD Career Center Greenhouses
-began setting up structure of testing report

Goals:
-set up testing site at MAST
-attach desal cone to plexi in a non-temperature-dependent way

Thursday, February 2, 2012

Log Thursday 2 February 2012

Accomplished:
-contacted Stevens and TCNJ re: testing environment
-wrote up mentor contact

Goals:
-set up MAST testing procedure
-continue looking for controlled testing environment

Tuesday, January 31, 2012

Log Tues 30 January 2012

Accomplished:
-contacted mentor re: testing procedure environment
-resubmitted midterm

Goals:
-research optimal NJ environments for testing
-recive MP3 rubric and set up MP3 calendar with due dates

Wednesday, January 25, 2012

Log Wed 25 January 2012

Accomplished:
-edited STEMM for minor grammatical errors
-recorded which testing procedures have already been completed

Goals:
-begin conducting final testing procedures

Monday, January 23, 2012

Log Mon 23 January 2012

Accomplished:
-researched TSA chapters in Arizona/New Mexico Area
-brainstormed project continuations for next year

Goals:
-refine Plan of Procedures for replication elsewhere
-more research on WHO would want to build this

Thursday, January 19, 2012

Log Thurs 19 December 2012

Accomplished:
-presented FPU for 2nd marking period

Goals:
-begin 3rd marking period work re: testing, revising.

Tuesday, January 17, 2012

Log Tues 17 January 2012

Accomplished:
-completed STEMM report and sent to mentor for review

Goals:
-present FPU for 2nd marking period

Thursday, January 12, 2012

Log Thurs 12 January 2012

Accomplished:
-completed FPU outline and practiced presentation
-added some illustrations to STEMM report (Science and Technology Sections)
-completed Mathematics section and part of Technology section of STEMM report

Goals:
-finish Technology section of STEMM report
-finish conclusion
-add more illustrations (esp. to Mathematics Section)
-send STEMM to Rob! v. Important before COB Friday!

Tuesday, January 10, 2012

Log Tues 10 January 2012

Accomplished:
-finished "Science" section for STEMM report
-wrote "Volumetrics" and "Evaporation Rate" subheadings for Mathematics section
-wrote majority of Conclusion for STEMM report (could not summarize unwritten sections, will add as they are completed)

Goals:
-complete"Technology" and "Mathematics" sections for STEMM report
-add illustrations where appropriate
-prepare for FPU

Thursday, January 5, 2012

Log Thurs 5 January 2012

Accomplished:
-consolidated more mentor contacts
-compiled works cited page (so far)
-finished "Engineering" heading for STEMM report

Goals:
-complete Science, Math and Technology headings for STEMM report
-prepare for FPU