Log Mon 23 January 2012

Accomplished:
-researched TSA chapters in Arizona/New Mexico Area
-brainstormed project continuations for next year

Goals:
-refine Plan of Procedures for replication elsewhere
-more research on WHO would want to build this

Thursday, January 19, 2012

Log Thurs 19 December 2012

Accomplished:
-presented FPU for 2nd marking period

Goals:
-begin 3rd marking period work re: testing, revising.

Tuesday, January 17, 2012

Log Tues 17 January 2012

Accomplished:
-completed STEMM report and sent to mentor for review

Goals:
-present FPU for 2nd marking period

Thursday, January 12, 2012

Log Thurs 12 January 2012

Accomplished:
-completed FPU outline and practiced presentation
-added some illustrations to STEMM report (Science and Technology Sections)
-completed Mathematics section and part of Technology section of STEMM report

Goals:
-finish Technology section of STEMM report
-finish conclusion
-add more illustrations (esp. to Mathematics Section)
-send STEMM to Rob! v. Important before COB Friday!

Tuesday, January 10, 2012

Log Tues 10 January 2012

Accomplished:
-finished "Science" section for STEMM report
-wrote "Volumetrics" and "Evaporation Rate" subheadings for Mathematics section
-wrote majority of Conclusion for STEMM report (could not summarize unwritten sections, will add as they are completed)

Goals:
-complete"Technology" and "Mathematics" sections for STEMM report
-add illustrations where appropriate
-prepare for FPU

Thursday, January 5, 2012

Log Thurs 5 January 2012

Accomplished:
-consolidated more mentor contacts
-compiled works cited page (so far)
-finished "Engineering" heading for STEMM report

Goals:
-complete Science, Math and Technology headings for STEMM report
-prepare for FPU

Tuesday, January 3, 2012

Log Tues 3 January 2012

Accomplished:
-consolidated mentor contacts
-posted pictures of final construction
-added some images to STEMM report
-organized headings/subheadings in STEMM report
-completed most of "Engineering" heading for STEMM report.

Goals:
-finish "System Type" and "Engineering Type" subheadings for STEMM report
-start writing up mathematics and science concepts for STEMM report
-contact TSA chapters in Arizona/New Mexico for possible testing??

Thursday, December 22, 2011

Log Thurs 22 Dec 2011

Accomplished:
-FINISHED CONSTRUCTION
-resarched leagile manufacturing

Goals
-send images to mentor
-add images to STEMM report
-write about innovation/open system for STEMM report

Tuesday, December 20, 2011

Log Tues 20 December 2011

Accomplished
-attatched outtake and intake pipes to barrel
-attatched funnel to intake pipe
-caulked edges of pipes

Goals
-paint outside of barrel

Friday, December 16, 2011

Log Fri 16 December 2011

Accomplished:
-affixed cone to plexi
-washed out barrel

Goals:
-adhere funnel to intake pipe
-attach intake/outtake pipes to barrel and seal edge
-procure last elbow joint

Wednesday, December 14, 2011

Log Wed 14 December 2011

Accomplished:
-cone did not properly adhere overnight
     -fixed cone (melting rather than epoxy)
-smoothed plexi circle edges
-wrote intro for STEMM report
-researched manufacturing methods for STEMM report and chose a combination of prefabrication, American system, lean, and agile manufacturing.

Goals:
-adhere cone to plexi
-add pipes to barrel
-wash out barrel.

Monday, December 12, 2011

Log Mon 12 December 2011

Accomplished:
-constructed cone


Goals:
-procure final elbow joint
-wash out barrel
-attach cone to plexi

Thursday, December 8, 2011

Log Thurs 8 Dec 2011

Accomplished:
-cut out plexiglass circle for desal cone
-cut out cavity in barrel top for cone
-prepared funnels for intake/outtake
-drilled holes for intake/outtake

Goals:
-construct desal cone
-procure extra elbow for added pipe length

Tuesday, December 6, 2011

Log Tues 5 December

Accomplished:
-added anti-splash insurance and stabilization structures to CAD drawings
-constructed intake and outflow pipes
-marked locations for intake and outflow holes
-marked up plexiglass circle, could not cut out due to equipment unavailability

Goals:
-cut out plexiglass circle and begin cone construction
-cut out intake and outflow holes

Friday, December 2, 2011

Log Fri 2 December 2011

Accomplished:
- finalized press release, added images, turned in
-contacted mentor
-waiting for Plan of Procedures authorization, construction phase delayed slightly

Goals:
-construct intake and outtake pipe

Wednesday, November 30, 2011

Log Wed 30 Nov 2011

Accomplished:
-edited press release
-turned in final plan of procedures for construction approval

Goals:
-construct intake pipe
-construct outflow pipe

Monday, November 28, 2011

Log Mon 28 Nov 2011

Accomplished:
-procured PVC, funnels, barrel, clear plastic for lid and cone, and adhesives for final product
-revamped cone design
-updated PoP re: cone design

Goals:
-procure bulkhead fittings for final product
-begin construction of intake/outtake pipes

Wednesday, November 23, 2011

Log Wed 23 Nov 2011

Accomplished:
-researched prices of all materials
-made cohesive shopping list so as not to waste Guiseppe's time
-collected some materials from lab

Goals:
-buy all materials
-begin construction

Monday, November 21, 2011

Log Mon 21 Nov 2011

Accomplished:
-contacted mentor
-finish press release
-finish calendar dates

Goals:
-assemble materials for final product
-begin construction

Friday, November 18, 2011

Log Fri 18 November 2011

Accomplished:
-short paragraph on assembly
-finished screenshots for step-by-step assembly and final product re: PoP
-added hinge to lid on CAD
-80% done with Press Release
-contacted mentor
-updated calendar schedules

Goals:
-Press Release
-obtain materials for final product!