Accomplished:
-finished S&D E report
Goals:
-begin poster for Design Presentation
Showing posts with label MP3. Show all posts
Showing posts with label MP3. Show all posts
Wednesday, March 7, 2012
Monday, March 5, 2012
Log Mon 5 March 2012
Accomplished:
-wrote most of SE report
Goals:
-finishe SE report
-add pictures to self evaluation report
-wrote most of SE report
Goals:
-finishe SE report
-add pictures to self evaluation report
Friday, March 2, 2012
Log Fri 2 March 2012
Accomplished:
-turned in testing report
-ran chemical analyses on water samples, water fulfills all chemical parameters
-began typing up outline for self & design evaluation
Goals:
-complete at least 3 parts of S&DE
-write up mentor contacts
-turned in testing report
-ran chemical analyses on water samples, water fulfills all chemical parameters
-began typing up outline for self & design evaluation
Goals:
-complete at least 3 parts of S&DE
-write up mentor contacts
Tuesday, February 28, 2012
Log Tue 28 February 2012
Accomplished:
-finished 96-hour testing period, collected device from testing site
-collected several water samples
Goals:
-run chemical analyses on water samples
-add results to testing report and finish conclusion
-finished 96-hour testing period, collected device from testing site
-collected several water samples
Goals:
-run chemical analyses on water samples
-add results to testing report and finish conclusion
Friday, February 24, 2012
Log Fri 24 February 2012
Accomplished:
-completed 24-hour testing period
-recorded results
Goals:
-complete 96-hour testing period
-record results
-completed 24-hour testing period
-recorded results
Goals:
-complete 96-hour testing period
-record results
Wednesday, February 22, 2012
Log Wed 22 February 2012
Accomplished:
-finalized permissions to test at MCVSD Career Center Greenhouses
-began assembling testing materials (pH strips, refractometer, coliform indicator etc)
-measured transport vehicle area to optimize positioning of device
Goals:
-complete testing 23-24 February
-complete Testing Report
-finalized permissions to test at MCVSD Career Center Greenhouses
-began assembling testing materials (pH strips, refractometer, coliform indicator etc)
-measured transport vehicle area to optimize positioning of device
Goals:
-complete testing 23-24 February
-complete Testing Report
Saturday, February 18, 2012
Log Fri 17 February 2012
Accomplished:
-added more pictures for testing report
-formulated agenda for testing days 23-24 February
Goals:
-find directions to testing site
-gain formal permissions to test
-begin gathering testing materials
-added more pictures for testing report
-formulated agenda for testing days 23-24 February
Goals:
-find directions to testing site
-gain formal permissions to test
-begin gathering testing materials
Wednesday, February 15, 2012
Log Wed 15 February 2012
Accomplished:
-Final Product awaiting grading
-Testing Stages Explanation Complete
-added some pictures to Testing Report
Goals:
-add more pictures to Testing Report
-Start Self Assessment Report
-Final Product awaiting grading
-Testing Stages Explanation Complete
-added some pictures to Testing Report
Goals:
-add more pictures to Testing Report
-Start Self Assessment Report
Monday, February 13, 2012
Log Mon 13 Febuary 2012
Accomplished:
-contacted MCVSD Career Center re: scheduling of testing
-Finished Testing Report Intro and Procedure List
-started Testing Report Stages Explanation
Goals:
-Testing Report Stages Explanation
-Final edits on final product
-contacted MCVSD Career Center re: scheduling of testing
-Finished Testing Report Intro and Procedure List
-started Testing Report Stages Explanation
Goals:
-Testing Report Stages Explanation
-Final edits on final product
Wednesday, February 8, 2012
Log Thursday 9 February 2012
Accomplished:
-contacted mentor
-set date for MCVSD Testing on 22 February 2012
Goals:
-contact MCVSD Career Center to finalize testing time/schedule/etc
-make final edits to final product in preparation for assessment
-continue writeup of Testing Report
-contacted mentor
-set date for MCVSD Testing on 22 February 2012
Goals:
-contact MCVSD Career Center to finalize testing time/schedule/etc
-make final edits to final product in preparation for assessment
-continue writeup of Testing Report
Monday, February 6, 2012
Log Mon 6 February 2012
Accomplished
-contacted mentor re: EcoComplex testing site
-recieved rubric and due dates and filled calendar schedule
-gained testing site permission from MCVSD Career Center Greenhouses
-began setting up structure of testing report
Goals:
-set up testing site at MAST
-attach desal cone to plexi in a non-temperature-dependent way
-contacted mentor re: EcoComplex testing site
-recieved rubric and due dates and filled calendar schedule
-gained testing site permission from MCVSD Career Center Greenhouses
-began setting up structure of testing report
Goals:
-set up testing site at MAST
-attach desal cone to plexi in a non-temperature-dependent way
Thursday, February 2, 2012
Log Thursday 2 February 2012
Accomplished:
-contacted Stevens and TCNJ re: testing environment
-wrote up mentor contact
Goals:
-set up MAST testing procedure
-continue looking for controlled testing environment
-contacted Stevens and TCNJ re: testing environment
-wrote up mentor contact
Goals:
-set up MAST testing procedure
-continue looking for controlled testing environment
Tuesday, January 31, 2012
Log Tues 30 January 2012
Accomplished:
-contacted mentor re: testing procedure environment
-resubmitted midterm
Goals:
-research optimal NJ environments for testing
-recive MP3 rubric and set up MP3 calendar with due dates
-contacted mentor re: testing procedure environment
-resubmitted midterm
Goals:
-research optimal NJ environments for testing
-recive MP3 rubric and set up MP3 calendar with due dates
Wednesday, January 25, 2012
Log Wed 25 January 2012
Accomplished:
-edited STEMM for minor grammatical errors
-recorded which testing procedures have already been completed
Goals:
-begin conducting final testing procedures
-edited STEMM for minor grammatical errors
-recorded which testing procedures have already been completed
Goals:
-begin conducting final testing procedures