Accomplished
-finished FPU Outline
-practiced FPU speech
Goals
-Present FPU!
-work on final plan of procedures
Monday, October 31, 2011
Friday, October 28, 2011
Final Materials List: Final Product (Desalination Component)
1 plastic barrel, approx. .9 m tall
1m of 4in (~10cm) PVC pipe
1 PVC bulkhead fitting
1 sq m flexible clear plastic
Epoxy adhesive (as needed)
Caulk (as needed)
NEXT
Log Fri 28 October 2011
Accomplished:
-shortened FPU speech to under 6 minutes
-printed out and turned in mentor contacts early!
-started calendar scheduling for MP2
Goals:
-Present FPU!
-contact mentor re: thoughts on scale model
-shortened FPU speech to under 6 minutes
-printed out and turned in mentor contacts early!
-started calendar scheduling for MP2
Goals:
-Present FPU!
-contact mentor re: thoughts on scale model
Wednesday, October 26, 2011
Log Wed 26 October 2011
Accomplished:
-finished FPU text
-uploaded scale model pictures
Goals:
-Streamline FPU speech
-finished FPU text
-uploaded scale model pictures
Goals:
-Streamline FPU speech
Scale Model
![]() |
| View of the open lid of the storage unit with UV lights |
![]() |
| Fitting between desalination unit and pipe to storage unit. |
![]() |
| Condensation cone |
![]() |
| Entire unit assembled. |
![]() |
| Interior of desalination component |
Monday, October 24, 2011
Materials Brainstorming: Final Product
Reservoir
- 1 large plastic tank
-recycled? from something
Cone
-flexible black plastic (shower sealer?)
Tubing
-PVC
Accessories
-bulkhead fitting valve
Adhesives
-epoxy resin
- 1 large plastic tank
-recycled? from something
Cone
-flexible black plastic (shower sealer?)
Tubing
-PVC
Accessories
-bulkhead fitting valve
Adhesives
-epoxy resin
Log Mon 24 October 2011
Accomplished:
-finished scale model construction
-wrote up final mentor contacts page
-edited HTML for post: Rationale Report in order to increase aesthetic value
-brainstormed materials for final product
-worked on FPU presentation text
Goals:
-finish FPU presentation text!!
-finished scale model construction
-wrote up final mentor contacts page
-edited HTML for post: Rationale Report in order to increase aesthetic value
-brainstormed materials for final product
-worked on FPU presentation text
Goals:
-finish FPU presentation text!!
Friday, October 21, 2011
Log Fri 21 October 2011
Accomplished:
-began scale model construction
-explained cone inversion edit
-edited html of several posts for aesthetic purposes
Goals:
-finish scale model construction
-work on FPU speech
-began scale model construction
-explained cone inversion edit
-edited html of several posts for aesthetic purposes
Goals:
-finish scale model construction
-work on FPU speech
Wednesday, October 19, 2011
Log Wed 20 October 2011
Accomplished:
-contacted mentor
-contacted other outside resources
-gathered materials for scale model
-edited Spec Check for Rationale Report
Goals:
-construct scale model
-finish FPU speech
-explain cone inversion edit
-contacted mentor
-contacted other outside resources
-gathered materials for scale model
-edited Spec Check for Rationale Report
Goals:
-construct scale model
-finish FPU speech
-explain cone inversion edit
Monday, October 17, 2011
Log Mon 17 October 2011
Accomplished:
-finished testing procedures writeup
-finished user analysis survey
-procured scale model materials
Goals:
-construct scale model
-work on FPU speech
-finished testing procedures writeup
-finished user analysis survey
-procured scale model materials
Goals:
-construct scale model
-work on FPU speech
Thursday, October 13, 2011
Log Thurs 13 October 2011
Accomplished:
-updated materials list for scale model
-updated isometric and exploded CAD drawings
Goals:
-begin writing up speech for FPU
-visit mentor, build scale model
-updated materials list for scale model
-updated isometric and exploded CAD drawings
Goals:
-begin writing up speech for FPU
-visit mentor, build scale model
Tuesday, October 11, 2011
Log Tues 11 October 2011
Accomplished:
- re-dimensioned orthographic drawings
- wrote up mentor contact (NJTEA Solar Panels Workshop)
-emailed mentor re: date for lab visit
Goals
-Visit mentor at lab this week, begin scale model construction
-procure materials for scale model?
- re-dimensioned orthographic drawings
- wrote up mentor contact (NJTEA Solar Panels Workshop)
-emailed mentor re: date for lab visit
Goals
-Visit mentor at lab this week, begin scale model construction
-procure materials for scale model?
Friday, October 7, 2011
Log Fri 06 October 2011
Accomplished:
-Added bulkhead fitting to AutoCAD 3-D drawing
-Attended NJTEA Solar Panel Conference
-Began planning to construct scale model at mentor's lab
Goals:
-set date to visit mentor's lab and begin scale model construction
-Added bulkhead fitting to AutoCAD 3-D drawing
-Attended NJTEA Solar Panel Conference
-Began planning to construct scale model at mentor's lab
Goals:
-set date to visit mentor's lab and begin scale model construction
Wednesday, October 5, 2011
Log Wed 5 2011
Accomplished:
-Turned in Solar Panel workshop and transportation permission slip
-Called mentor & took notes - revamped design
-added visuals to research post
-edited 3-D AutoCAD drawing and updated posts of orthographic, isometric, and exploded views.
Goals:
-Write up questions for Solar Panel Workshop
-Email mentor with revamped design and dimensions
-Begin assembling scale model materials
-Turned in Solar Panel workshop and transportation permission slip
-Called mentor & took notes - revamped design
-added visuals to research post
-edited 3-D AutoCAD drawing and updated posts of orthographic, isometric, and exploded views.
Goals:
-Write up questions for Solar Panel Workshop
-Email mentor with revamped design and dimensions
-Begin assembling scale model materials
Monday, October 3, 2011
Log Mon 3 October 2011
Accomplished
-Updated Calendar
-Emailed Mentor
-Consolidated Mentor Contacts
Goals
-Call mentor tomorrow!!
-Updated Calendar
-Emailed Mentor
-Consolidated Mentor Contacts
Goals
-Call mentor tomorrow!!
Subscribe to: