Thursday, December 8, 2011

Log Thurs 8 Dec 2011

Accomplished:
-cut out plexiglass circle for desal cone
-cut out cavity in barrel top for cone
-prepared funnels for intake/outtake
-drilled holes for intake/outtake

Goals:
-construct desal cone
-procure extra elbow for added pipe length

Tuesday, December 6, 2011

Log Tues 5 December

Accomplished:
-added anti-splash insurance and stabilization structures to CAD drawings
-constructed intake and outflow pipes
-marked locations for intake and outflow holes
-marked up plexiglass circle, could not cut out due to equipment unavailability

Goals:
-cut out plexiglass circle and begin cone construction
-cut out intake and outflow holes

Friday, December 2, 2011

Log Fri 2 December 2011

Accomplished:
- finalized press release, added images, turned in
-contacted mentor
-waiting for Plan of Procedures authorization, construction phase delayed slightly

Goals:
-construct intake and outtake pipe

Wednesday, November 30, 2011

Log Wed 30 Nov 2011

Accomplished:
-edited press release
-turned in final plan of procedures for construction approval

Goals:
-construct intake pipe
-construct outflow pipe

Monday, November 28, 2011

Log Mon 28 Nov 2011

Accomplished:
-procured PVC, funnels, barrel, clear plastic for lid and cone, and adhesives for final product
-revamped cone design
-updated PoP re: cone design

Goals:
-procure bulkhead fittings for final product
-begin construction of intake/outtake pipes

Wednesday, November 23, 2011

Log Wed 23 Nov 2011

Accomplished:
-researched prices of all materials
-made cohesive shopping list so as not to waste Guiseppe's time
-collected some materials from lab

Goals:
-buy all materials
-begin construction

Monday, November 21, 2011

Log Mon 21 Nov 2011

Accomplished:
-contacted mentor
-finish press release
-finish calendar dates

Goals:
-assemble materials for final product
-begin construction